Arapahoe Bridge over Big Dry Creek Replacement Project

image of a road with the words Arapahoe Road over Big Dry Creek

Reconstruction of the bridge on Arapahoe Road, east of University Boulevard is underway. The existing bridge over Big Dry Creek was originally constructed in 1945 and is past its useful life. The Arapahoe Road Bridge project will replace the existing bridge with a wider and taller structure, improve pedestrian access over and around the bridge, and make improvements to the Big Dry Creek waterway. Construction is expected to take 18 months to complete.


Project Update (June 2022)

In June, crews have various bridge activities planned, including drilling and pouring caissons on the south side of the Arapahoe Road bridge, building forms and pouring abutment concrete, and installing rebar. Work hours are from 7 a.m. to 6 p.m., Monday through Friday. One lane of traffic will be maintained in each direction during construction. Please pay attention while driving in the work zone and never drive distracted. Motorists should expect increased Arapahoe County Sheriff patrols in neighborhoods north and south of Arapahoe Road to manage cut-through traffic.

All construction activities are weather-dependent and subject to change for the safety of crews and the traveling public.

Road closures should be expected during the project. Prior to any closures an announcement will be sent to advise the public of alternate travel routes. People living in the nearby neighborhoods will still be able to get to their homes. To stay informed, sign up for our project announcements here, or follow us on social media @CentennialGov.

Upcoming Construction Impacts:

  • May 31 through June 12 – In the next two weeks, crews plan to finish drilling and pouring bridge caissons on the south side of the Arapahoe Road bridge.
  • Remainder of June – Through June, crews will continue bridge work including building forms for abutments, installing rebar and pouring abutments. In addition, the team will continue to install the storm sewer infrastructure.
  • Ongoing – Traffic continues to travel in new lane configurations to accommodate construction. One lane will be provided in each direction throughout the duration of this construction phase – August 2022. Detour routes on University Boulevard and Dry Creek Road are highly encouraged. 

Detour routes on University Boulevard and Dry Creek Road are highly encouraged.

The pedestrian/bike path is closed for the duration of the project. VIEW THE DETOUR MAP

View the project flyer(PDF, 254KB).

View images of construction.

This reconstruction project will:

  • Replace the existing bridge with a wider and taller structure
  • Improve pedestrian access over and around the bridge
  • Make improvements to the Big Dry Creek drainage and waterway system

  • Project Schedule

    Construction is expected to be complete in spring 2023.  All work will be weather-dependent and will be subject to change.


    Project Map

     

    map of project area

  • Stay Informed

    Sign-up to receive project news and updates.

     

    Questions?

    Hotline: 720-758-8298

    Construction Team (Benesch): Ryan Garringer, PE Construction Engineer rgarringer@benesch.com