Permits & Licenses for Developers

Commercial building icon

Are you a developer looking to build in Centennial? Interested in changing your existing zoning? In this section you will find information about Centennial's land development process, zoning information and required permitting.

Land Development Process

Step 1.Pre-Submittal Application

Determination of process, fees, referral requirements and opportunities for comments and questions. Learn more about Development Pre-Submittals.

Step 2.Land Development Application Submittal and Review

Review and comment of site plan/plat/public improvement agreement (PIA), etc. Public Hearings (if required) scheduled after all comments are substantially addressed. Learn more and apply for a Development Permit.

Step 3.Construction Drawings (CDs)

Submitted after at least one round of site plan review. Can be submitted concurrently with site plan if no public hearing is required. Learn more about Site-Civil Construction Documents.

Step 4.Building Permit

Submitted after at least one round of Construction Drawings (CDs) are reviewed. Issued at or after Development Permit. Learn more and apply for a Building Permit.

Step 5.Pre-Construction Meeting

Scheduled prior to construction. Meeting covers construction hours and restrictions, contractor/City contact and inspection processes.

Step 6.Development Permit

Issued upon completion of land development application process, completion of CDs, and submittal of collateral for PIA public engineer's cost estimate (ECE).

Step 7.75% Walkthrough

Walkthrough with City, Southeast Metro Stormwater Authority (SEMSWA), Fire Safety, Building Division, etc. to resolve any issues before Certificate of Occupancy can be issued.

Step 8.Probationary Acceptance

Reduction in collateral associated with the PIA public engineer's cost estimate (90%). Hold remaining 10% for two years.

Step 9.Final Acceptance

Final 10% collateral is released two years after probationary acceptance, project is accepted and closed.

Permits

Building Permits

Building permits are required for new buildings, renovations and additions to existing buildings to ensure all structures within the City are safe to occupy. Visit the Building Permit page for more information. 


Fence Permits

A permit is required for all new fences and the replacement of existing fences where height, location or materials are changing (e.g., chain link to wood). Visit the Fence Permit page to learn more.


Sign Permits

A permit is required for all new signs and replacement of or modifications to existing signs. Signage allowed is based on the zoning of the property. Properties are zoned under the Land Development Code and sign regulations are governed based upon Article 6, Signs and Lighting. Visit the Sign Permit page to learn more.


Streets - Right-of-Way Permits

A Right-of-Way (ROW) Permit is required for all construction and maintenance within the City’s ROW such as placing dumpsters on residential streets or requesting a street closure or transporting oversized/overweight loads on City streets.

Visit the Right-of-Way Permit tab on the Public Works page to learn more about the different types of ROW permits issued by the City.