The Jones District History/Timeline

Jones review process slide 1
 
Jones review process slide 2
 
Jones review process slide 3
 
Jones review process slide 4
 
Jones review process slide 5
 
Jones review process slide 6
Jones review process slide 7
 
jones8_update.jpg
 
 
jones9_update.jpg
 
 

1. Developers Presented Vision to City Council

December 3, 2018

The presentation was informational only. No formal request was made, and no decision was made. 

Presentation Highlights: 

-  Significant growth is expected in the Denver South Metro region by 2035 

-  The Jones District is Centennial’s best opportunity to accommodate this growth and compete in the South I25 corridor for jobs, investment, and identity

- The Regulating Plan needs to be amended to make The Jones District more competitive


2. Small Group Meeting #1 with HOA Representatives

February 21, 2019

City staff and the development team met with a group of 10 representatives from HOAs in the area to gain an initial understanding of opportunities and constraints associated with future development at The Jones District. 


3. Pre-Submittal Meeting 

March 6, 2019

The development team met with City Staff and Southeast Metro Stormwater Authority (SEMSWA) to discuss the proposed Regulating Plan amendments, learn about the process and requirements, and share feedback received from the small group. 


4. Community Meeting 

March 28, 2019

The development team shared their vision and solicited feedback from meeting attendees.

Meeting announcements were provided 2 weeks prior to:
- Contacts for registered neighborhoods and civic associations within 1 mile
- CenCON
- Adjacent property owners within 200 ft of site

Meeting information was also shared on Centennial’s social media channels. 


5. Formal Submittal: Staff & Public Review  

First submittal received May 10, 2019

The development team submits proposed Regulating Plan amendments to City Staff and stakeholders for review. Once all City Staff comments are addressed, public hearings will be scheduled. 

Who Reviews?
- City Staff
- Residents who provided their email addresses
- Contacts for registered neighborhoods and civic associations within 1 mile
- CenCON
- SEMSWA
- Cherry Creek School District 
- Arapahoe Library District
- South Suburban Parks and Recreation District 
- Southgate Water and Sanitation District
- Cherry Creek Basin Water Quality Authority
- Urban Drainage and Flood Control District
- South Metro Fire Rescue District
- Arapahoe County Sheriff’s Office
- Southeast Public Improvement Metro District
- Panorama Metro District
- Regional Transportation District
- Colorado Department of Transportation
- Centennial Airport
- Arapahoe County
- CenturyLink
- Xcel


6. Small Group Meeting #2 with residents

May 30, 2019

City staff and the development team met for a 2nd time with the small group members to review the submittal and address any outstanding concerns.


7. Small Group Meeting #3 with residents

Sept. 12, 2019

City staff and the development team met for a 3rd time with the same small group members to review the submittal and address any outstanding concerns.


8. Planning & Zoning Commission Public Hearing 

Oct. 2019 (complete)

The Planning and Zoning Commission will determine if the proposed Regulating Plan amendments meet the criteria listed in the Land Development Code and either recommend approval or denial to City Council. 

Meeting announcements will be shared with the same people and in the same format as the Community Meeting. 


9. City Council Public Hearing 

Nov. 2019 (complete)

City Council will determine if the proposed Regulating Plan amendments meet the criteria listed in the Land Development Code, and either approve or deny the amendments. 

Meeting announcements will be shared with the same people and in the same format as the Community Meeting.